Seven companies have announced transformer factories or transformer plant expansions in the United States so far in 2026, and their announcements add up to 3,012 jobs, according to Location Decision's Tracker. Five of the seven disclosed an investment figure. Those five total about $979.6 million.

Transformers are the equipment that steps power up and down between the transmission grid and the customer. Every new factory, data center campus and subdivision needs them, and utilities have been waiting years for large units. That makes these plants one of the clearest signals in the Tracker of where the grid supply chain is being built.

The list

In order of announcement, with figures as each company or state released them:

Company and location

Announced

Investment

Jobs

What it makes

Timeline given

ERMCO, Waddell, Ariz.

Jan. 21

Not disclosed

More than 500

Three-phase distribution transformers

Operational in 2027

Feb. 5

$18.4 million (equipment, first two years)

110 within five years

Solid-state transformers

Not stated

Virginia Transformer, Muscle Shoals, Ala.

May 19

Not disclosed

1,100 at full production

Power transformers, 2 to 500 MVA

Production January 2028

Sept. 15

$528 million

654

Small power transformers

Production in 2029

Sept. 29

More than $71 million

73 new (146 retained)

Large liquid-filled power and specialty transformers

Not stated

GE Vernova, Shreveport, La.

Nov. 10

$34.5 million

175 direct new

Industrial and renewable energy transformers

Full capacity in 2028

Nov. 17

$327.7 million

400 new

Heavy-duty power transformers

Online early 2028

How LD counted

LD pulled every 2026 announcement in the Tracker whose main product is a transformer, then checked each figure against the company or state release. The jobs total adds the stated numbers: ERMCO's "more than 500" counts as 500, Virginia Transformer's 1,100 is the plant's headcount at full production, Amperesand's 110 are expected within five years, and Niagara Power Transformer's 73 new jobs exclude the 146 it is keeping. The investment total is 528 + 327.7 + 71 + 34.5 + 18.4 million dollars, from the five companies that gave a figure. The Tracker logs decisions of at least $50 million or 100 jobs, so smaller expansions are not here. Plants that make related grid gear, such as Siemens Energy's high-voltage switchgear plant in Pearl, Miss., are also left out.

What the list shows (LD analysis)

The Southeast holds most of it. Four of the seven plants, in Alabama, Mississippi, Louisiana and South Carolina, account for 2,329 of the 3,012 jobs and $890.2 million of the disclosed investment. Mississippi's announcement came from the Mississippi Development Authority, which called Hitachi Energy's Copiah County project the company's largest transformer manufacturing investment in the U.S. Arizona's came from the Arizona Commerce Authority, and Amperesand's Reno plant appeared in a tax abatement release from Nevada's Governor's Office of Economic Development.

The capacity is mostly still ahead. Of the five plants that gave a date, one expects to operate in 2027, three point to 2028 and Hitachi Energy's Gallman line is scheduled to start production in 2029.

Why it matters

For anyone siting a large project, transformer supply sets part of the schedule. Wood Mackenzie's second-quarter 2025 survey put average lead times for power transformers at 128 weeks, about two and a half years, as reported by POWER. The firm had projected supply deficits of 30% for power transformers and 10% for distribution transformers in 2025. LD's Grid Desk shows hookup schedules already stretching on the customer side: in PPL's latest Pennsylvania grid plan, six of eight big hookups are projected to come online 8 to 19 months after customers asked.

The plants also bring hiring needs to places such as Gallman, Muscle Shoals and Gaffney. For suppliers, each plant is a new buyer of copper and electrical steel. The workforce side of the grid build-out is the subject of LD's look at how a rural Virginia college built a pipeline of 753 line workers.

What to watch

The next tests are whether the 2028 and 2029 start dates hold and whether more transformer makers announce U.S. plants. LD adds new announcements to the Tracker as they come and will update this count.