PPL Electric Utilities' 2026 local transmission plan, filed with grid operator PJM on Oct. 6, lists eight customer requests for new high-voltage service in eastern and central Pennsylvania that add up to about 7,930 megawatts of eventual load.
The same filing shows how far apart customer timelines and utility timelines can be. For six of the eight requests, PPL projects the transmission work will be in service later than the date the customer asked for, by 8 to 19 months. Those six account for about 6,030 MW. The other two, totaling 1,900 MW, are projected to be ready in the month requested.
PPL's own cost figures for the work tied to the eight requests sum to about $1.06 billion. Each request carries a "Transmission Cost Estimate" in the filing, ranging from $13.5 million to $231.65 million.
What the filing shows
PPL projected in-service | Requests | Eventual load (MW) | Transmission cost estimate |
|---|---|---|---|
2027 | 2 | 2,480 | $209.1 million |
2028 | 6 | 5,450 | $849.9 million |
Total | 8 | 7,930 | $1,059.0 million |
Source: PPL, Submission of Supplemental Projects for Inclusion in the Local Plan, 2026 (PJM TEAC, Oct. 6, 2026). Totals are LD sums of PPL's per-request figures.
The requests start small and grow. Their first-year loads, as PPL lists them, total 1,540 MW. Each customer's stated load then ramps up to its full size between 2029 and 2033. The largest single request is approximately 1,980 MW by 2033; the smallest is approximately 450 MW by 2030.
How LD counted
LD's Grid Desk counted every request in PPL's local plan submission whose project driver is "Customer Service" and whose stated facility load is 100 MW or more, and checked each figure against the PDF. These are requests and planned transmission work, not finished hookups: PPL labels the transmission solutions "Conceptual" for at least seven of the eight. The delay figures compare each customer's requested in-service month with PPL's projected in-service date for the related transmission project. The filing does not name the customers or say what the facilities are, so LD makes no claim about who they are or what they will build.
Why it matters
Pennsylvania's power demand is being counted several ways at once, and the numbers measure different things. PPL said in its third-quarter results on Nov. 6 that its data center pipeline stands at about 35.3 gigawatts "in advanced stages of planning," including 11.4 GW under signed electric service agreements and 8.5 GW under construction. The large-load adjustment PPL asked PJM to plan for in its 2027 forecast is 32,089 MW (filed Sept. 29 and not yet approved by PJM), as shown on LD's Pennsylvania state page.
LD analysis: the local plan is the narrowest of these counts. It covers only the requests that have reached a specific transmission design, with a cost and a projected date attached. For companies weighing a Pennsylvania site, and for the economic developers recruiting them, the gap in this filing is the practical point: a requested power date and the utility's projected date for the wires can sit more than a year apart, and the second one is the date a project can plan around.
The pattern is not unique to PPL. Among the Dominion Energy data center delivery points in Virginia that LD's Grid Desk has checked against Dominion's 2026 local plan, three are projected 33 to 47 months after the customer's requested date.
LD's Tracker follows announced Pennsylvania projects, including large data center campuses such as Amazon's AI Innovation Campus in Salem and Falls townships. The PPL filing does not say whether any of its eight requests is tied to an announced project, and LD does not match them. The full list of Pennsylvania projects in the Tracker is on the state hub.
What to watch
PPL presented more supplemental projects at PJM's Mid-Atlantic subregional meetings on Oct. 16 and Nov. 12; LD's Grid Desk is checking those filings now. Also watch PJM's 2027 load forecast, which will show how much of the requested Pennsylvania load the grid operator builds into its planning, and whether PPL's projected dates hold in its next local plan.